2009-03-10View Original

Thread Content

If you are a project design manager (project leader): 1. What would you do if your designers fail to complete their work on time (for example, failing to submit design specifications or final documents by the due date)? Will his bonus be deducted, or... 2. If your designers complete a task ahead of schedule, would you give them a reward? This post was last edited by hutom123 on 2009-3-24 16:22.]
Reply #22009-03-10
1. The designers hand it over to the professional Lead for management. If a particular task is falling behind schedule, conduct a thorough analysis and make proactive adjustments. If it’s a matter of personal attitude, replace the person promptly. 2. Project awards will not be given to individuals. Team building is a good way. It seems your question is directed at the professional lead, who doesn’t have the authority to impose rewards or penalties directly.
Reply #32009-03-10
Design is a systematic project that requires the proper leadership of a project manager and the concerted efforts of a team in order to be completed on time. Before the design begins, a project plan coordination sheet must be prepared, with clear time allocations for each task, which is then signed off by the responsible professional. If a designer fails to complete the work on time without a valid reason (which generally doesn’t happen), I will talk to them and ask them to finish it according to the original plan. I might also go along with their requests, or even meet some of their unreasonable demands, just to avoid disrupting the overall progress. But once this project is completed, if there are other projects in the future, I won’t want this person to work with me again.
Reply #42009-03-10
The project manager usually presses the person in charge of the technical aspects directly, and does not deal with the designers themselves. If the task is completed, a bonus will still be given based on the amount of work done on the drawings, but no additional bonuses will be provided. The key point is that they certainly won’t work with him on the next project. For those who complete the task ahead of schedule, I will consider giving them a higher bonus percentage, and I will let them know that they will be given more opportunities in the future

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.