Is this arrangement considered to be \"setting up a Class C warehouse within a factory building\"”

2009-03-10View Original

Thread Content

There is a single-story building separated in the middle by a fire wall; one side is used for storing Class C materials, while the other side serves as a production workshop. Is this arrangement in line with the requirements specified in the Building Code regarding the establishment of Class C warehouses within factory buildings?”
Reply #22009-03-10
After checking against the Building Code, I believe it cannot be determined simply by looking at whether the warehouse storing Class C items has safety exits and evacuation routes, as well as whether the building meets the required fire resistance standards. If these two conditions are not met, it should be considered that: \"A Class C warehouse is located within a factory building.\"”
Reply #32009-03-10
3.3.10 When Class C warehouses are installed within a factory building, they must be separated from the building using firewalls and floor slabs with a fire resistance rating of not less than 1.50 hours. When Class D and Class E warehouses are installed, they must be separated from the factory building using non-combustible partition walls with a fire resistance rating of not less than 2.50 hours and floor slabs with a fire resistance rating of 1.00 hour. The fire resistance rating and area of the warehouse shall comply with the provisions of Articles 3.3.2 and 3.3.3 of these specifications.
Reply #42009-03-10
I agree with what the original poster said.
Reply #52009-03-10
I also agree with the original poster’s view; it should be considered a Class C warehouse located within a factory building, as the factory and the warehouse are part of the same structure. Clause 3.3.10 specifies that a firewall and floor slabs with a fire resistance rating of no less than 1.50 hours must be used to separate it from the factory building, and what the original poster mentioned meets these requirements as well – there is a firewall in between. Therefore, I believe it constitutes a Class C warehouse set up within a factory building.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.