Thread Content
The installation of the utility instruments for a certain project has been largely completed, and it is about to enter the commissioning phase. Offline testing (single-circuit testing) is originally part of the commissioning process for individual subsystems and should be carried out by specialized commissioning firms; however, the project owner now requires our construction team to develop a plan, with the commissioning firm being responsible for the acceptance process. Since I’ve never done this before, I don’t have any information available. I would be extremely grateful if any expert could provide some reference materials!
Here is a table of contents for your reference. This is the protection test plan for the cold-state commissioning of desulfurization systems in a power plant. 1. Project Overview 2. Basis for Preparation 3. Cold-state commissioning tasks for the FGD system 4. Cold-state commissioning plan for the FGD subsystems: (i) Adjustment and testing plan for flue gas dampers; (ii) Testing plan for aeration fans and inspection of aeration tanks; (iii) Testing plan for seawater booster pumps and adjustment of water flow in the absorption tower; (iv) Commissioning plan for booster fans; (v) Commissioning plan for flue gas heat exchangers (GGH). 5. Cold-state commissioning plan for the FGD system: (i) Cold-state ventilation test plan; (ii) ESD function test plan. 6. Organizational structure 7. Personnel preparation 8. Safety measures