Division of tasks between electrical and instrumentation personnel: In chemical plants, power distribution grounding and lightning protection grounding are undoubtedly the responsibility of electricians. Then, is shielding grounding and anti-static grounding for instruments also handled by electricians?
It is best for the two to work together on the installation
This should be done by the electrical department. But you need to set conditions for the instrument. Discuss with the electrical department on how to proceed.
As the saying goes, electricity and instrumentation are inseparable; therefore, it cannot be simply determined whether it is electrical equipment or instrumentation that is involved. I think for high-voltage electricity (above 220VAC), it definitely relates to electrical systems, while low-voltage electricity at 24VDC is generally used in instruments. As for the \"shielding grounding and anti-static grounding on the instrument panel\" you mentioned, the electrical system provides the busbars to the instrument control panel; the rest is handled by the instruments themselves.
The grounding for the instruments should be handled by the instruments themselves; the electrical department is only responsible for the distribution panel
The instruments in our factory are connected by the instruments themselves! I think they should be done together!
Electrical and instrumentation teams work together, with the instrumentation taking care of it in the end.
It depends on the work requirements of your organization. Since electrical work and instrumentation work are separated, the instrumentation part should naturally be handled by those specialized in instrumentation. Of course, if the workload is too large and they cannot complete it on their own, they can discuss collaborating to finish it