For piles with more than two lifting points, why should the orientation of the pile tips be determined based on the pile driving sequence when prefabricating on site?

2009-03-26View Original

Thread Content

For piles with more than two lifting points, why should the orientation of the pile tips be determined based on the pile driving sequence when prefabricating on site?
Reply #22009-03-26
The ground of the prefabricated site must be flat, compacted, and protected from water logging and subsidence. For piles with more than two lifting points, when prefabricating on site, the orientation of the pile tips must be determined according to the pile driving sequence, because when the piles are lifted into place, the pulley groups on the pile frame are divided into left and right. If the orientation of the pile tips is inappropriate, it is very difficult to temporarily turn around.
Reply #32009-03-26
Because when the pile is lifted into place, the pulleys on the pile frame are divided into left and right sides. If the pile tip is not oriented appropriately, it will be very difficult to make a temporary U-turn.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.