Thread Content
For example, during the project design process, if a requirement is submitted by a upstream department to a downstream department, and the downstream department finds issues with that requirement and sends it back to the upstream department, which then makes adjustments before sending it back again. This back-and-forth process involves a time delay. Generally, however, there is only one time constraint for each requirement in a project; if a requirement has to be sent back and forth 3–4 times, it will affect the project schedule. Some say that it is possible to control the edition through conditions, but certain conditions may only refer to one edition without the need for any modifications. Let’s discuss what better ways there are to address the issue of controlling round-trip conditions
We are a small design firm; any conditions have to be discussed among all relevant departments to minimize mistakes, and this approach works very well.
The design conditions involve control at specific time points, and some conditions may need to be repeated several times; this is a common scenario in design. If there is enough time and good cooperation among everyone, it should not be a problem. If time is tight and the specialist proposing the conditions keeps changing them, things will get complicated. In fact, the most important aspect of design is coordination among everyone involved. As mentioned above, discussing things together is also a good way to solve problems; it can at least reduce the need for back-and-forth communication. There is also a simple method: simply make modifications to the original design conditions, and then have the person who proposed them sign and date it, as re-submitting everything takes some time after all. If there are too many changes, it is necessary to analyze whether the person proposing these conditions has the capability to handle this task, or whether the conditions themselves are not yet fully developed; in such cases, it should be considered whether to assign someone else to the task or to adjust the design plan. This post was last edited by fanxh on 2009-3-29 21:56]
Our approach is that when the party setting the conditions hands them over, the receiving party does not simply sign to accept them and that’s it. Instead, initially check whether there are any issues with these conditions; if so, request that they be modified immediately before submitting them again. Secondly, once the design drawings have been produced, if changes are needed due to altered conditions, it depends on the specific situation; if it does not affect subsequent work, no changes may be necessary. Make changes in the next design phase. If modifications are necessary at this stage, it is also acceptable to make them manually and then sign.
The control of design parameters in your company is quite thorough; one should examine them carefully before accepting them, but generally this isn’t done. Often, things are taken in first, and only when a problem is discovered is someone turned to you, which results in wasted time.
If the conditions need to be changed and it delays the design process, demand payment for rework from him; that way he will be more careful next time.
I believe it is necessary to establish a strict approval system among various specialties under the supervision of the project manager, along with a responsibility system for joint review.
To ensure strict control over design plans and quality assurance, a design condition control sheet should be prepared before the design process begins, and it must be signed off by the person in charge of each specialty. The process of preparing the design condition control table represents each specialist’s understanding of the project’s design process and scope, as well as their overall grasp of the required design timeline. During the design phase, strict adherence to this control table is essential; at the weekly meetings, the effectiveness of its implementation is assessed, and any conditions that may cause delays are identified in advance. When repeated changes to certain conditions lead to delays in the design progress, new plans must be formulated based on the actual situation, and if necessary, the subsequent design schedule should be adjusted to ensure that all designers feel a sense of urgency ; To control the quality of the specified requirements, specific standards for design quality should be set at the beginning of a project, including requirements regarding the content and depth of such requirements. These standards should be reiterated during design meetings to ensure that they meet the needs of the downstream teams carrying out their work, thereby avoiding repeated revisions to the requirements ; Furthermore, those responsible for condition verification must take their responsibilities seriously and not just sign off carelessly, ensuring that the quality of the conditions is maintained ; For those who meet the requirements, if their design input criteria are not satisfied, it must be brought to attention immediately, and a request should be made for professional adjustments. If necessary, the issue should be discussed and decided upon by the project team; it must not be ignored until the project team needs the drawings and then it is discovered that the requirements are not met and design work cannot proceed. This would significantly impact the design timeline ; Since the vast majority of engineering companies, under the influence of traditional habits, have designers who never pay attention to deadlines, they tend to shift responsibility when design progress is affected – either claiming there’s too much work and not enough staff, or that the required materials are delivered late. In such situations, the project team must not only raise the designers’ awareness of time management but also take charge of progress control itself; it cannot simply act as a passive observer and ignore things once deadlines are set, as ultimately it is still the project that is at stake. The project team can ask the project engineers to prepare condition registration forms, record the times when these conditions are issued and returned, and set a time limit for the response time from the relevant departments (for example, two days). This helps to standardize everyone’s work through established procedures and ensures that progress control is based on clear records. Furthermore, whenever conditions permit, it is advisable to organize more team-building activities so that professionals can get to know one another; working in a pleasant environment improves communication efficiency. Sometimes, issues that could be resolved over a phone call need not be brought up at regular meetings, thus saving design time. In short, condition control involves many aspects and numerous interfaces, but as long as the project team members raise their awareness of controlling these conditions, it is still possible to keep the design schedule on track.
Repeated revisions during the design process are entirely normal; such considerations should be taken into account at the planned milestones, and generally, the timing of revisions needs to be addressed at the major control points. As for feedback on the conditions, acceptance of those conditions is taken as the standard; minor adjustments can have their timing negotiated directly, while major changes require approval from the project manager in order to extend the submission deadline.
Both the edition and date are provided for reference. Time is the ultimate reference point; regardless of the version, the conditions must be submitted by this time. This is mainly the responsibility of the team leader; you need to have an understanding of your subordinates’ capabilities. It’s advisable to ask newcomers to submit their requirements in advance, giving them time to process them. Within the profession, it’s best to check the conditions first to avoid any embarrassment. When facing major challenges, professionals from various fields can sit together and discuss the matter.
In my opinion, before the conditions are proposed, the person who proposes them and the recipient should communicate and work together more closely, as sometimes the proposer is not aware of the conditions desired by the recipient, nor whether the proposed conditions are suitable for them. Additionally, it is essential to conduct a review and obtain signatures before the conditions are put forward