How to design supports for gas pipes with very high temperatures

2009-03-29View Original

Thread Content

When designing pipes for high temperatures, how should the supports be designed? How should expansion joints be installed?
Reply #22009-03-29
Pipelines with temperatures usually above 400 degrees require stress analysis calculations, and the relevant conditions should be submitted to the piping engineering team. When submitting these conditions, an initial pipe rack layout can be provided. If the piping engineering calculations show no issues, the original plan can be used; otherwise, adjustments must be made based on the feedback received. Additionally, expansion joints, spring frames, etc., are all provided by the piping and machinery specialty based on the results of stress analysis calculations.
Reply #32009-03-30
I suggest you follow the advice of your seniors and provide materials for the stress analysis to determine the location and type of the pipe supports.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.