Why aren’t check valves installed on each branch of the plant’s low-pressure flare line?

2009-03-29View Original

Thread Content

Why aren’t check valves installed on each branch of the plant’s low-pressure flare line? During the purging of the flare main pipe, each branch acts as a dead end
Reply #22009-03-29
Each branch pipe is equipped with a isolation valve, and its pressure is generally higher than that of the main low-pressure gas pipeline. During cleaning, each branch pipe can clean the main pipe simultaneously, with the lowest point of the main pipe being vented.
Reply #32009-03-29
What was said on the second floor is correct; during purging, the main pipeline can be used for purging as well, with each branch line being emptied
Reply #42009-03-29
The pressure in the torch line is too low; sometimes this prevents the check valve from operating, and it also makes it impossible to ensure that the check valve remains in good working condition at all times.
Reply #52009-03-29
Can water seals and molecular seals be used?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.