Construction issues in oil depot areas

2009-03-29View Original

Thread Content

I would like to ask the experts: during the construction of a tank farm, are the grounding grid and underground pipeline networks constructed simultaneously, starting right after the site is leveled?
Reply #22009-03-29
The grounding grid can be installed quickly with a small volume of work, so it can be delayed slightly.
Reply #32009-03-30
During the construction of the tank farm, the grounding grid and underground pipeline network can be constructed simultaneously

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.