What circumstances warrant the use of pipeline water flushing before commissioning a newly installed unit?

2009-03-30View Original

Thread Content

What circumstances warrant the use of pipeline water flushing before commissioning a newly installed unit?
Reply #22009-03-30
The first step is sometimes done with water; generally, steam, nitrogen, or air is used, and chemical cleaning is also an option
Reply #32009-03-30
It depends on the process requirements; only those methods that allow the use of water can be employed. For example, our refrigerant systems cannot be cleaned with water – using water for cleaning should be the simplest approach
Reply #42009-03-30
Simply put: anything that can undergo a hydrostatic test requires water flushing.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.