The company is about to carry out instrument installation, including tray installation, piping installation, valve installation, on-site instrument installation, and so on. What else should be prepared during the installation process in addition to following industry standards? How to negotiate with the installation company? Please share your valuable experiences together. I am on the owner’s side. This post was last edited by wwxxss_1 on 2009-3-30 10:55.]
Construction preparation for instrument installation projects: The construction of instrument systems can be divided into the construction preparation phase, the instrument installation phase, the phases of supporting individual unit tests and joint tests, and the handover and acceptance phase. The preparation phase before construction is the starting point of the instrumentation project, during which all preliminary construction preparations must be carried out. This stage is a transitional phase that connects engineering design with the actual construction of engineering projects. The main task at this stage is to create the conditions for the smooth commencement of the project and for orderly construction to proceed thereafter. The first step in instrument installation work is preparation for construction, as this preparation forms the basis for the installation process. The adequacy of the work carried out at this stage has a decisive impact on the overall quality of the installation and the progress of the construction. Those with construction experience all agree that seven parts preparation are needed for every part of actual work, which shows the importance of preparation in construction. 1. Contents of construction preparation The contents of preparatory work should be determined based on the requirements and conditions of the project. Generally, construction preparation includes the following: (1) Establishing a construction organization structure – assigning personnel to various positions. (2) Technical preparation — preparation of technical documents, establishment of a quality assurance system, safety measures. (3) Material preparation — Submit plans for main construction materials and consumable materials. (4) Preparation of construction machinery and standard instruments — Submit a plan for the machinery and standard instruments. (5) Develop a construction plan — — Create a construction network plan. (6) Construction temporary facilities — In accordance with the overall site layout, temporary facilities are established at the construction site, such as offices, rest rooms, warehouses, prefabrication areas, and temporary power supplies.
It’s not clear whether the poster represents the owner’s side or the general contractor’s side. Is the construction company acting as a general contractor or is it only responsible for the actual construction work? If it’s a general contractor, then things are easier for the owner – all that’s needed is to be prepared to oversee the process and carry out regular quality checks. If construction, design, and procurement are handled separately, with the owner managing them themselves, then the task is to coordinate everything properly and resolve any issues that arise during construction.