Today, a technician from a construction company brought over the change order that we sent to the client a few days ago, saying that it didn’t have the client’s signature on it. Putting aside the fact that the procedure he used to return it to our design institute was incorrect, I would like to ask everyone: is it necessary for the client’s signature to be on the change order? ?
Reply #22009-03-30
The construction party has only a contractual relationship with Party A; without Party A’s signature, there is a risk of not receiving payment for the work done, in addition to having to take on responsibility. There is no contractual relationship with the designer, and it has no legal validity. The normal procedure should be that the designer sends the changes to Party A for approval (signing); once Party A signs to agree, it is sent to the construction party, who, if they deem it feasible, will sign and proceed with the work.
Reply #32009-03-30
The client must sign! Since general changes involve adjustments to the budget and additional materials, etc., without the client’s signature, who will cover these costs?
Reply #42009-03-30
There are various reasons for design changes; if it is caused by the designer, the owner’s signature is not required; If the change is caused by the owner, it shall be signed and confirmed by the owner. Sometimes design changes also result in increased costs, and in such cases it depends on the contracting arrangement to determine whether the owner’s approval is required.
Reply #52009-03-30
This change was proposed by Party A. At that time, the change order we provided to Party A did not have any space for their signature, but the change order was intended for the construction unit. How can it be sent to the construction unit if Party A does not agree to it? ? ? Could someone send me the format for change orders at your company? Thank you!
Reply #62009-03-30
Let me address this properly first: the \"construction unit\" should refer to Party A, that is, the client; what the building owner actually means is the technicians from the \"construction company\"... Even if there is no space for the construction unit to sign on the change order, there should at least be a place for the supervision unit to sign. Any change to the drawings alters the content intended by the original drawings, and such changes need to be approved, even if no additional costs are involved.
Reply #72009-03-30
Although there is a homeowner confirmation section, it remains empty when the homeowner’s approval is not required. (There is a design institute name at the top, which has been omitted.) Notice of Design Change. Number: Project name, Site name, Project code, Original drawing number, Specialty, Page number out of total pages. Reason for change: Details of modifications: Attachments. Design representative or person making the change, Reviewer, Head of the representative team or reviewer, Purchasing manager, Construction manager, Cost (manager) engineer, Owner’s confirmation. Note: For projects that are not under general contracting, it is not necessary to fill in the entries for Purchasing manager, Construction manager, and Cost (manager) engineer. Indicated by a “/”. To: CC: Date: The last edit of this post was made by fanxh on 2009-3-30 at 13:35.]
Reply #82009-03-30
This change order should be structured like this: the client requests a change, sends a signed authorization letter to the design firm; upon receiving this letter, the design firm issues the change order to the client, who then assigns the construction work to a construction company. The construction contractor may request the owner to sign, but has no right to take the change order back to the design institute.
Reply #92009-03-30
Thank you to all of you for your help; it was only then that I realized there were defects in this change order – the signing section only provided spaces for the compilation, proofreading, and approval tasks by our design institute, with no space reserved for anything else. It makes sense that the technicians from the construction company refused to accept it. We will definitely make improvements in the future.:handshake

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.