Let’s discuss the issues with the furnace walls of the newly commissioned 6-meter coke ovens. (Premium)

2009-04-07View Original

Thread Content

For the newly commissioned 6-meter coke ovens, with 20 chambers, the bottom parts of the east and west walls show severe wire stripping, with a depression of about 1 centimeter. What is the cause of this? Does that expert know?
Reply #22009-04-08
There could be various reasons: 1. The masonry quality is poor, with severe misalignment in that area. 2. The quality of the bricks is problematic, or the bricks were too wet during construction. 3、There is a problem with the furnace heating process; the temperature in this area did not rise as planned.
Reply #32009-04-09
I think the main issue is with masonry, and another one is furnace drying.
Reply #42009-04-09
One or all of them? If it’s just one, it might be a problem with the bricks or an issue that occurred during baking; if it’s all of them, then it’s likely a problem related to the baking process

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.