I work in the project department of an engineering company, where I am responsible for controlling the progress of projects. I wasn’t very familiar with project management before, and now I want to know what tasks are involved in managing project progress – things like creating schedules, drawing Gantt charts, holding progress meetings, etc. Are there any other tasks as well, such as preparing progress balance sheets? Additionally, what knowledge do I need to learn? Please help me understand these aspects. This post was last edited by laiqi on 2009-4-10 at 13:46
Planning and statistics, construction scheduling, civilized construction management, etc.
First, it’s necessary to determine whether you are the general contractor or the client. If you are the client, then all the things you mentioned are related to image-building; no matter how good that image may be, if the construction party does not cooperate, it remains just theoretical. What needs to be done now is to keep an eye on the construction party, as well as control the timing of material delivery. By managing these two aspects properly, progress can be ensured. If you are the general contractor, there is even more that needs to be controlled. First, you need to coordinate resources with the client, including funds and materials. Secondly, you must manage your own staff and work areas, establish a reasonable sequence of construction tasks, and ensure the proper allocation of resources. There is a lot to do. In short, progress control is achieved by carrying out the planned tasks with the right resources within a reasonable time frame
1. First, it is necessary to understand the processes involved, that is, how many processes are included in each project. 2. It is important to know the time allocation for each process, that is, to determine how much time is required for each one. 3. One must also be aware of the number of workers needed for each process. 4. Understanding the construction sequence is essential, so that tasks can be carried out in a coordinated manner. 5. It is crucial to obtain accurate information from actual conditions; standard quotas may not be suitable, and they must be adjusted according to the specific circumstances of the construction unit. 6. Only in this way can a proper schedule be prepared. A schedule is a dynamic document that needs to be updated continuously based on the actual situation
You need to understand almost all aspects of construction. Civil engineering, electrical systems, instrumentation, piping, equipment, steel structures, and so on – in addition, it is necessary to be aware of the manufacturing cycle for the equipment as well as the delivery times. That’s not something that can be done in just a little time.
As the people mentioned above said, I’m not sure whether I am the client or the contractor. Our model is BOT, which means we use someone else’s facilities and conditions, but we provide the funding, manage the project ourselves, hire supervisors, select construction teams, and operate the project. However, we need the cooperation of steel mills, glass factories, cement plants, etc. After earning profits, we transfer the project equipment to those partners such as steel mills. So, we can be considered the owners during both the construction and operation phases, but we still need the cooperation of partners like steel mills in many aspects, as well as supervision from supervisors and construction teams. It’s very complicated; we also have to deal with **, and there’s little information available. I’ve never done this before, so I can only figure things out on my own. It seems that many tasks aren’t done properly, resulting in a lot of time wasted and a lot of unnecessary effort. I really hope that experienced professionals who have worked on similar projects can offer some guidance
You should be the client; you put forward your requirements, and ask the construction team to submit their construction plans and schedules. There should also be a person in charge at a higher level to whom you can seek advice. You are merely someone responsible for monitoring the progress of the project – all you need to do is follow the instructions given and keep checking things regularly
It’s the same for us; there’s a lot of work to be done. Since you are the owners, you need to decide whether the construction method for this project will be EPC or something else. If not, then some of the project management tasks will have to be carried out by you, the client side. I’m not very familiar with this area either; I can only suggest that you learn more about project management
You are dealing with BOT, which is a relatively complex form of project management. First, it’s necessary to understand what BOT means: BOT is an abbreviation for Build-Operate-Transfer, and it is usually translated as “build-operate-transfer”. This translation is straightforward, but it fails to reflect the essence of BOT. BOT is essentially a method for investing in, constructing, and operating infrastructure; it is based on an agreement reached between the government and private entities, whereby the government grants a concession to those private entities, allowing them to raise funds over a certain period to build a particular infrastructure and to manage and operate that infrastructure as well as the related products and services. **The quantity and price of the public goods or services provided by this institution can be restricted, but private capital must be guaranteed the opportunity to earn profits. The risks throughout the process are shared by ** and private entities. When the concession period comes to an end, the private entity transfers the facility to the **department** as agreed, so that it can be operated and managed by the department designated by **. Therefore, the term BOT is more appropriately translated as “infrastructure concession”. The above describes the narrow concept of BOT. BOT has evolved over hundreds of years, and to adapt to different conditions, many variants have emerged, such as BOOT (Build‑Own‑Operate‑Transfer), BOO (Build‑Own‑Operate), BLT (Build‑Lease‑Operate), and TOT (Transfer‑Operate‑Transfer), among others. The broad concept of BOT includes these derivatives as well. What people usually refer to as BOT is likely the broad concept of BOT. “The term “build-operate-transfer” cannot encompass the development of the BOT model. Therefore, as project managers for BOT projects, it is necessary to have more knowledge. First, it is important to understand the relationships between all parties involved. Second, we need to identify what contradictions exist at this stage, which ones are within our control and which ones are not. And then go and do it, only then can you
What is learned from books seems shallow after all; to truly understand something, one must put it into practice. Many things are based on experience; if no one shows you how to do them, you have to figure it out on your own.
Same problem; luckily, I have someone to guide me
This has to start from scratch; it’s very difficult for an inexperienced newcomer to do this job well
It is crucial to break down the project task packages and carry out Earned Value calculations on time. Only by knowing the EV and comparing it with the planned values can we gain a clear understanding of the project’s progress, which in turn enables effective progress control.
1. One should have a certain understanding of the process flow of the projects under management; 2. Proficient in using various project management tools: WBS, Gantt charts, single-node and double-node network diagrams, etc ; 3. Proficient in using various common computer software: Project/P3/Excel/Visio/Word, etc ; 4. Willing to endure hardship, diligent in using one’s mind, and skilled in taking action ; 5. Good at coordination, sincere in dealing with others, and possesses excellent moral qualities. The above are my main requirements for the control manager, for your reference. This post was last edited by yxbj on 2009-4-11 16:33]
You must understand the costs! Progress control without cost control is simply nothing! Many people don’t understand this, which is why they can’t earn high salaries~
No matter which type of progress control you use, you need to do the following: 1. Study the contract and clarify the scope of work 2. Develop a reasonable and actionable plan (including design, procurement, and construction). . . . Therefore, you need to have a general understanding of the knowledge in various fields.) 3. For the schedule, conduct tracking and corrective actions, provide deviation reports to all parties, and hold meetings to resolve issues. That’s about it; as a newcomer, the most important thing is to learn as much as possible*.
Is the poster referring to cost control or progress control? From what I’ve experienced with progress control (during the construction phase), it basically involves preparing a progress report on a weekly or monthly basis, collecting data on the actual amount of work completed from the construction party, and handling the approval processes for payment related to the construction progress; As for creating a Gantt chart or something for the early stages of construction, tools like P3 or PROJECT can be used for that ;