How is the environmental impact assessment of a new project inspected and accepted?

2009-04-08View Original

Thread Content

My unit has a new chemical project. The project's environmental impact assessment report was prepared and submitted for approval based on a production capacity of 1 million tons, but the project was constructed based on 500,000 tons. How will the environmental impact assessment be accepted after the project is completed, because various data have changed. Please give expert guidance!
Reply #22009-04-08
There are treatment equipment and processes, inspections, and final discharge locations.
Reply #32009-04-11
This is big trouble. According to regulations, the completion acceptance of the project is based on the environmental impact assessment report approved by the environmental protection department. If the scale does not meet the requirements, the completion acceptance cannot be carried out. You must go to * * Relevant departments will re-register.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.