What should you pay attention to when opening holes in diesel storage tanks?

2009-04-08View Original

Thread Content

Our company needs to add a fuel level gauge to the diesel storage tank and make holes in the tank. Could you please give me some guidance on the safety issues that need to be paid attention to?
Reply #22009-04-08
Cleaning and replacement qualified, flammable gas detection
Reply #32009-04-08
After I drain the diesel from the storage tank, I pump out the combustible gas inside and check that the combustible gas meets the standards. Do I still need to clean it? Is this step of cleaning necessary?
Reply #42009-04-08
one: Isolate and lock both: Exclude remaining diesel fuel ; three: Clean the tank. four: Detect oxygen and its flammable gases. five: Supply air (open all valves) and monitor oxygen ; six: Safe voltage lighting. seven: If there is welding, disconnect the existing ground connection.
Reply #52009-04-08
For the top opening of the storage tank, after taking measures such as replacement and cleaning on the fourth floor, you can consider filling it with water, and then perform fire opening operations on the top.
Reply #62009-04-08
Prepare work instructions 1. Pour process, empty the medium in the tank. 2. When handling temporary electricity use procedures, first use natural ventilation and then forced ventilation. ; 3. Pour in water and alkali and cook with steam. The time depends on the size of the tank. ; 4. Open the light-transmitting hole for ventilation ; 5. Testing. Detectors must correctly wear prescribed protective equipment (respirators, safety ropes, etc.) to detect flammable gases. The upper, middle, and lower parts of the tank must be taken separately. The detection location must be representative. ; 6. Test fire ; 7. The opening of the liquid level gauge is usually at the top. A layer of sand can be spread on the bottom and filled with water if possible.
Reply #72009-04-08
(Additional 7th floor) Disconnect valves connected to other containers, add blind plates, lock the valves or arrange for special supervision; Before entering the tank, you should also apply for a "Confined Space Entry Permit" and provide safety education to workers. Install anti-static devices.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.