I would like to ask the engineers: What should the form for documenting the completion of insulation work look like, and what information should it include? This post was last edited by laiqi on 2009-4-13 15:17]
Check the construction and acceptance standards for thermal insulation projects; they contain relevant tables. The specifications outline various acceptance criteria, indicating to you how to conduct the inspections.
Table J115 in SH3503-2002 (Sinopec acceptance specifications) can be used; it is primarily used to specify the conditions to be confirmed prior to insulation application (such as the status of paint application, etc.).
Is insulation required for the circulating water pipeline in the gas separation unit area? Thank you! !
First, records of inspections for concealed works must be kept; second, records of inspection and acceptance for insulation work procedures must be maintained.
Hidden works must be inspected, accepted, and documented before they are concealed, as clearly stipulated in relevant standards. The procedures carried out before insulating equipment or pipelines are considered concealed works.
SH 3503–J115 Record of Hidden Works Project Name: Unit Name: Project Category: Hidden Works Drawing Number Content and schematic diagram of hidden works Inspection results Construction/Supervision Unit Construction Unit Professional Engineer: Date Quality Inspector: Technical Supervisor: Team Leader: Date
It is specified in GB 50126-2008, Code for Construction of Thermal Insulation Works for Industrial Equipment and Piping