What is the purpose of building fire protection design fire protection audit?

2009-04-13View Original

Thread Content

What is the purpose of building fire protection design fire protection audit? Is there any charge?
Reply #22009-04-13
It is a pre-procedure for fire protection acceptance, which is equivalent to a "preliminary" concept. It mainly reviews the fire protection layout drawings to see whether they meet the requirements.* * Standard requirements (mainly refers to fire protection standards such as GB50016 and GB50160)
Reply #32009-04-13
Generally, you can entrust the drawing review company to carry out the review, and the fee is of course included. The plan review company is responsible for the review, and the fire department relies on the plan review company's opinions. Of course, they can also raise questions. Only after this is passed can the construction drawing design be carried out. The subsequent fire protection acceptance requires an intermediary company to evaluate and issue a fire protection facility audit report before acceptance.
Reply #42009-04-13
There is no charge for fire protection audit of building fire protection design
Reply #52009-04-13
Administrative approval. The main thing is to review the fire protection layout drawings to see if they meet the requirements. * * Standardize requirements and issue fire protection audit opinions. Fire inspection will be carried out after completion.
Reply #62009-04-13
The fire protection audit of building fire protection design is carried out in accordance with the provisions of the Fire Protection Law of the People's Republic of China. Please refer to the latest fire protection law for specific provisions.: Article 10 in accordance with * * For construction projects whose fire protection technical standards require fire protection design, unless otherwise provided in Article 11 of this Law, the construction unit shall, within seven working days from the date of obtaining the construction permit in accordance with the law, submit the fire protection design documents to the fire protection agency of the public security organ for record, and the fire protection agency of the public security agency shall conduct random inspections.   Article 11 For large-scale crowded places and other special construction projects specified by the public security department of the State Council, the construction unit shall submit the fire protection design documents to the fire protection department of the public security organ for review. The fire protection department of the public security organ shall be responsible for the results of the review in accordance with the law.   Article 12 If a construction project that is subject to fire protection design review by the fire protection department of the public security organ according to law has not been reviewed in accordance with the law or fails to pass the review, the department responsible for reviewing and approving the construction license of the project shall not grant a construction license, and the construction unit or construction unit shall not carry out the construction work. ; If other construction projects fail to pass the random inspection according to law after obtaining the construction permit, the construction shall be stopped.   Article 13 According to * * Upon completion of a construction project that requires fire protection design according to engineering construction fire protection technical standards, fire protection acceptance and filing shall be carried out in accordance with the following provisions:   (1) For construction projects stipulated in Article 11 of this Law, the construction unit shall apply for fire protection inspection and acceptance to the fire protection department of the public security organ. ;   (2) For other construction projects, the construction unit shall report to the fire protection department of the public security organ for record after acceptance, and the fire protection department of the public security organ shall conduct random inspections.   Construction projects that are subject to fire inspection and acceptance in accordance with the law are prohibited from being put into use without fire inspection and acceptance or if they fail to pass the fire protection inspection and acceptance. ; If any other construction project fails to pass the random inspection in accordance with the law, its use shall be stopped.   Article 14 The specific methods for fire protection design review, fire protection acceptance, filing and spot inspection of construction projects shall be prescribed by the public security department of the State Council.
Reply #72009-04-14
There is no charge, and the audit will be used as the basis for acceptance. After the audit is completed, the fire department will issue an audit opinion letter and stamp it to take effect.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.