Cross-tasking: lifting steel beams at heights and installing equipment pumps underground – how to protect the pumps?

2009-04-15View Original

Thread Content

Concurrent work: lifting steel beams from a height while installing equipment below—pumps. How to protect the pumps?
Reply #22009-04-15
It’s easy – last time, we used the scaffolding from the event to cover the pump completely with crowbars.
Reply #32009-04-15
1. Is the height and other dimensions of the mobile scaffold the same as those of a pump? 2. Is the pry board an ordinary wooden board? 3. Is the mobile scaffold constructed using ordinary steel pipes? How to name the event?
Reply #42009-04-15
1. The projection area must be larger than that of the device. 2. The use of wooden prying boards is not allowed here; all prying boards must be made of galvanized steel. 3. Mobile scaffolding, also known as portal scaffolding, does not require assembly; it can be set up simply in one go, which is very convenient. A scaffold built with steel pipes is called a vertical pole scaffold, and it takes some time to set up.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.