How many months after the detailed design of the project can the key pump data be released? Take the 1 million tons of methanol project as an example. In a few months, will the key pump parameters be available for equipment bidding?
Reply #22009-04-15
You should get it after the preliminary design is completed, especially if it requires introduction or long-term ordering. Some even start ordering before the preliminary design is approved.
Reply #32009-04-15
The key pump parameters can be obtained during the initial design. If you wait until the detailed design of the project, it will be too late! For some relatively mature processes, they can be obtained before initial design.
Reply #42009-04-15
It can be determined by preliminary design according to normal conditions.
Reply #52009-04-16
Three months after the preliminary design, key pump data and long-term equipment data sheets can be obtained for bidding and ordering.
Reply #62009-04-17
Is the data feasible? Is there any risk?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.