Gentlemen, does anyone know the procurement and installation timelines for various instruments? Debugging cycle. Thank you
Reply #22009-04-16
That’s a great topic; I want to know too. Generally, for domestic instruments, it takes about a month; for control valves, it takes a bit longer, around 2 to 3 months. Abroad, this time doubles.
Reply #32009-04-16
Imported valves take about 4 to 6 months, while domestic valves take about 2 to 3 months. Flow meters, transmitters, temperature and pressure gauges: around one month; cables: around one week; cable trays: around half a month; imported DCS systems: 4 to 6 months; domestic DCS systems: 2 to 3 months. The above refers to bulk orders; for small quantities, the situation varies depending on whether the manufacturer has the items in stock or whether the production lead time is short.
Reply #42013-03-01
You’ve covered it quite comprehensively! I learned it! ! !

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.