Thread Content
What are the administrative licensing procedures required for the fire protection aspect of a petrochemical project with an investment of 1 billion yuan, and what are the relevant legal bases? How is the program below? Is the trial production phase carried out before the fire safety inspection? ? ? 1. General layout fire protection review ; 2. Construction can proceed only after the fire safety inspection of each unit is completed and approved ; 3. Construction of fire protection facilities ; 4. Inspection of fire protection facilities.
There will be some differences among various provinces and cities. For detailed information, please go to the **Administrative Licensing Center** in your project location for inquiries.
Petroleum chemical projects == Hazardous chemical projects; Fire safety issues == “Three simultaneities”. 1. Economic and Planning Commission: Approval for project establishment. 2. Work Safety Supervision Bureau: 2.1 Approval for project initiation (preliminary safety assessment); 2.2 Review of design for safety facilities; 2.3 Filing of trial production plan; 2.4 Inspection (safety assessment). 3. Public Security Fire Department: 3.1 Review of design for fire protection facilities; 3.2 Fire protection inspection. 4. Health administration department: 4.1 Approval for project initiation (preliminary assessment of occupational hazards); 4.2 Review of design for occupational health protection facilities; 4.3 Inspection of occupational health protection facilities. 2.2, 3.1, and 4.2 are carried out before construction; 2.3 and 4.3 are carried out before trial production; 2.4 is carried out after trial production, after which the license is obtained.
The fire protection procedures for hazardous chemical projects mainly include preliminary fire safety inspections, electrical testing and building fire prevention inspections after completion, as well as final fire protection inspections. Fire safety inspections and approvals are carried out by the local fire department (or brigade) and fall under the category of administrative permits, whereas testing is done by fire safety agencies (which are intermediary organizations) and does not constitute an administrative permit.