Is it mandatory that safety pre-assessment and safety acceptance assessment be carried out by different safety assessment agencies? In other words, cannot the same assessment agency conduct both the safety pre-assessment and the safety acceptance assessment for the same company? **Are there any documents on this matter?
Order No. 29 issued by the Chief Safety Supervisor: To ensure the fairness of safety assessment results, the safety pre-assessment and safety acceptance assessment for the same construction project must not be carried out by the same intermediary agency; The design agency shall also not conduct safety assessments on the construction projects it designs.
Is there such a rule? I see that many companies use the same evaluation agency. I wonder who can provide the source of the specific regulations.
According to relevant regulations, it is best for evaluations to be carried out by different assessment agencies; however, in practice, there are also cases, and not a few at that, where the same assessment agency conducts the evaluations.
This provision is included in the General Rules for Safety Assessment, but the wording used is “it is advisable,” meaning it is not mandatory. In reality, the preliminary evaluation and acceptance evaluation of a project are often carried out by the same evaluation agency, which allows them to be better familiar with the project’s specifics, thereby facilitating the acceptance process.
It’s only now that I realize that for Unified Enterprises, pre-evaluation and acceptance evaluation should ideally be carried out by different evaluation agencies. Yet in reality, it is often the same evaluation agency that conducts the assessments, as companies are willing to do so and the agencies do not want to lose their existing clients.
It seems there is no rule prohibiting a single organization from conducting the evaluation, and for the integrity of the entire project, it is more convenient to have one organization handle it.
In reality, it is common for a single evaluation agency to handle the preliminary assessment, evaluation, and final acceptance of a project
Although it is stipulated that \"3. To enhance the fairness of safety assessment results, the safety pre-assessment and safety acceptance assessment for the same construction project shall not be carried out by the same intermediary agency.\"; The design agency shall also not conduct safety assessments on the construction projects it designs. ”Notice on Issuing the Outline for Compiling the \"Safety Section\" in the Preliminary Design of Non-coal Mine Construction Projects, as Well as the Forms Related to the Review of Safety Facility Designs and the Completion Inspection (Safety Supervision General Administration Document No. 29). General Administration of Work Safety, Document No. 29 -------------------------------------------------------------------------------- Notice on Issuing the Outline for Compiling the “Safety Section” in the Preliminary Design of Non-coal Mine Construction Projects, as Well as the Forms Related to the Review of Safety Facility Designs and the Completion Inspection Various provincial, autonomous region, and municipal work safety supervision bureaus, as well as the Xinjiang Production and Construction Corps: In order to further ensure proper implementation of the requirement that safety facilities in non-coal mine construction projects be installed simultaneously with the construction itself, in accordance with the relevant provisions of the “Measures for the Review of Safety Facility Designs and the Completion Inspection of Non-coal Mine Construction Projects” (formerly Order No. 18 issued by the Work Safety Supervision Bureau, hereinafter referred to as Order No. 18), our bureau has formulated an outline for compiling the “Safety Section” in the preliminary design of such projects, as well as the forms required for the review of safety facility designs and the completion inspection. These documents are now being issued to you; please comply with them. The relevant matters are notified as follows: First, in order to ensure the safe production of non-coal mining enterprises from the source, all regions must enforce laws strictly and strengthen supervision over the design review and completion inspection processes. For non-coal mining enterprises that fail to implement the requirement of installing safety facilities simultaneously with construction projects, corresponding measures shall be taken in accordance with the provisions of Order No. 18. Tailings ponds represent a major hazard source for non-coal mining enterprises; the design review of safety facilities and the completion inspection for their construction, renovation, expansion, closure, as well as the recycling of tailings after closure, must be carried out in accordance with the provisions of Order No. 18. II. The design of safety facilities for non-coal mine construction projects shall be carried out by design units with the appropriate qualifications. For construction projects of small open-pit quarries with an annual extraction volume of less than 500,000 tons and a maximum mining depth of no more than 50 meters, the design of safety facilities can be carried out by mining engineering technology service agencies that have been accredited by safety production supervision and management departments at the provincial level or above. III. To enhance the fairness of safety assessment results, the safety pre-assessment and safety acceptance assessment for the same construction project shall not be carried out by the same intermediary agency ; The design agency shall also not conduct safety assessments on the construction projects it designs. IV. In accordance with the provisions of the \"Decision of the State Council on Canceling a Second Batch of Administrative Approval Items and Changing the Management Methods for a Number of Administrative Approval Items\" (State Council Document No. 5), the evaluation of safety pre-assessment reports for construction projects is carried out by social intermediary agencies ; The work safety supervision and management department is responsible for filing the safety pre-assessment reports that have undergone evaluation. Among them: For construction projects to be reviewed by the state council’s department in charge of work safety supervision and management, the evaluation of their safety pre-assessment reports shall be carried out in accordance with the relevant regulations set forth by that department (see Attachment 8) ; For projects subject to review by local work safety supervision and management departments, the procedures for evaluating the safety pre-assessment reports are determined by the provincial work safety supervision and management departments themselves. To improve efficiency and reduce the burden on enterprises, in line with the procedures for construction project management and the actual requirements of safety supervision, the review and filing of safety acceptance evaluation reports can be carried out simultaneously with the completion acceptance of safety facilities. V. For new construction, renovation, and expansion projects of non-coal mines that come online after November 1, 2002, the safety facilities must undergo design review and completion inspection in accordance with the provisions of Order No. 18. The work safety supervision and management department shall not issue a work safety license to any entity that has not passed the design review for safety facilities or the completion inspection. Attachments: 1. Outline for preparing the “Safety Section” in the preliminary design of metal and non-metal mine construction projects; 2. Outline for preparing the “Safety Section” in the preliminary design of onshore oil and gas construction projects; 3. Outline for preparing the “Safety Section” in the preliminary design of offshore oil and gas construction projects; 4. Outline for preparing the “Safety Section” in the preliminary design of oil and gas pipeline construction projects; 5. Application form for filing the safety pre-assessment report for non-coal mine construction projects; 6. Application form for reviewing the design of safety facilities in non-coal mine construction projects; 7. Application form for the completion inspection of safety facilities in non-coal mine construction projects; 8. Catalogue of documents related to the review and filing of safety pre-assessment reports. April 29, 2005. In practice, however, both are usually signed together, which results in a lower price.
In our Shanxi province, there is basically one company that handles this task; they do it perfunctorily, hardly checking the site at all, and their work is always identical. But as long as it’s them who carry out the work, the Provincial Work Safety Supervision Bureau approves it.
We both do things in pairs; there aren’t such strict requirements!