Successful feeding of gasification process in Xinnengda Banner

2009-06-21View Original

Thread Content

This post was last edited by shanxg on 2009-6-22 at 16:38 to offer congratulations; we ask the experts from that factory to share their insights
Reply #22009-06-21
Where did you get this information? Do you know what the product is after syngas is produced?
Reply #32009-06-21
Please ask those who are aware of the situation to talk about the specifics
Reply #42009-06-22
The XinAo gasification unit was successfully started up on the evening of June 20.
Reply #52009-06-22
Which gasification technology is being used?
Reply #62009-06-22
Congratulations on the successful commissioning of the 600,000-ton methanol project in Xinaodalat Banner! This project has many friends, and I hope its successful progress will bring good luck to each of them!
Reply #72009-06-22
Were both furnaces brought online, or was only one brought online?
Reply #82009-06-22
The Ordos 600,000-ton methanol project has a total investment of 2.4 billion yuan. It includes 3 boilers with a design pressure of 9.8 MPa and a capacity of 168 tons each, as well as 2 air separation units with a capacity of 45,000 cubic meters per hour. The project utilizes Texaco’s water-coal slurry pressurized gasification technology, with 2 gasifiers in operation and 1 as a backup. The project started on June 8, 2006, and was completed by the end of 2008 (the construction and commissioning periods were very long). Its subsequent product is a 400,000-ton dimethyl ether plant.
Reply #92009-06-22
XinAo truly achieved success on the first attempt at feeding the material! I’m not quite sure about the details; perhaps a colleague from SNOW Energy could explain it?
Reply #102009-06-22
It seems that during the first feed, the slurry circulation valve was not opened, which caused the pressure in the slurry pump hose to reach 17 MPa and led to its rupture!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.