What equipment is needed in the early stages of furnace drying?

2009-07-30View Original

Thread Content

RT The furnace drying phase for the second-phase coking project at our plant has already begun. Could you please advise on what equipment is required?
Reply #22009-08-15
When heating the furnace, devices such as thermocouples can be rented, which is cheaper than buying them outright. And it becomes invalid once you buy and use it; at least you won’t need that much of it. I suggest you rent the equipment
Reply #32009-08-15
Equipment required for furnace drying: 1. According to the requirements of the furnace manufacturer or those related to equipment management, appropriate thermocouples should be installed to assist in controlling the drying curve, and a recorder should be used to automatically log the data. 2. Prepare an infrared portable detector for measuring the temperature of the furnace and its related components, in order to detect any abnormalities promptly.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.