Questions regarding GB50160-2008

2009-08-10View Original

Thread Content

The Code for Fire Protection Design of Petrochemical Enterprises has been in effect since July 1, 2009. What should we do with projects that are designed before implementation and then inspected after implementation?
Reply #22009-08-10
What was said upstairs is correct. But then, the person in charge will end up working for nothing, so it’s necessary to keep updating oneself and staying informed about the regulations
Reply #32009-08-11
If you have completed the relevant design before the new standards are issued (but not yet implemented), it should be approved in accordance with the old standards; you can consult the local authorities to obtain their approval and permission.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.