The last edit to this post was made by zhangyong6404 on 2009-9-3 at 23:05. What exactly does the concept of \"three checks and four fixes\" in the chemical industry refer to? Those with experience in the chemical sector, please share your insights; I’m new to this industry
Reply #22009-09-03
It should be three checks and four fixes, right? Three inspections and four determinations: Three inspections: Check for omissions in the design, identify potential issues with construction quality, and examine unfinished work. Four fixations: Determine tasks for the issues identified during the inspection, identify the units and personnel responsible for handling them, determine the corrective actions to be taken, and set deadlines for completing the corrections.
Reply #32009-09-03
The three checks and four fixes are a procedure in the intermediate handover process of projects.
Reply #42009-09-04
The three inspections and four determinations are generally standard procedures used during the construction phase, aimed at ensuring that the project is completed successfully and safely through effective and comprehensive oversight throughout the construction process. Three checks: check for design omissions, check for potential issues in construction quality, and check for unfinished projects. Four fixations: Determine tasks for the issues identified during the inspection, identify the units and personnel responsible for handling them, determine the corrective actions to be taken, and set deadlines for completing the corrections. If the original poster is in charge of the project, they should report more issues in the form of material specifications during the construction process.
Reply #52009-09-04
The “three inspections and four determinations” in engineering construction refer to: checking for missing items in the design, examining the quality of the work and any potential hazards, and reviewing the amount of work that remains unfinished. For the issues identified, tasks are assigned, personnel are designated, deadlines are set, and measures are established to ensure that these issues are resolved within a specified time frame. However, there is also an explanation for the four fixations as: fixing the personnel, fixing the measures, fixing the time, and fixing the funds.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.