[Ammonia Synthesis Knowledge] Daily Question (06) 2009.12.26

2009-12-25View Original

Thread Content

The maximum score for this activity is 10 Wealth; please, moderators, do not assign scores above this limit. When replying to a post, hide the answers – scores will not be given if the answers are not hidden. Specific hiding method: http://bbs.hcbbs.com/viewthread.php?tid=492556&highlight=%D2%FE%B2%D8 Posts that have been edited are not rated. (All questions are taken from the \"Question Bank for Vocational Workers’ Training – Fertilizer Production Operators.\" An electronic version of this book is available for download in the soda ash information sharing area at http://bbs.hcbbs.com/thread-13140-1-2.html) 1. In the Brown process, the process condensate is discharged without undergoing stripping treatment. ( ) 2. After replacing the high-pressure steam preheating coil, it must be purged with steam. ( ) 3. In a fire-tube waste heat boiler, the tube sheet on the high-temperature side is more prone to damage than that on the low-temperature side. ( ) 4. Once a leak in the waste heat boiler is detected, the plant must be shut down for maintenance. ( ) 5. In the Brown process, during normal operation, the combustion air in the first furnace is cold air. ( )
Reply #22009-12-26
In the Brown process, the process condensate is discharged without being stripped. (Yes) 2. After replacing the high-pressure steam preheating coil, it must be purged with steam. (Yes) 3. In a fire-tube waste heat boiler, the tube sheet on the high-temperature side is more prone to damage than that on the low-temperature side. (Yes) 4. Once a leak in the waste heat boiler is detected, the plant must be shut down for maintenance. (Incorrect) 5. In the Brown process, during normal operation, the combustion air in the first furnace is cold air. (True)
Reply #32009-12-26
1. Wrong 2. Right 3. Right 4. Right 5. Wrong
Reply #42009-12-26
1. In the Brown process, the process condensate is discharged without being stripped. (Incorrect) 2. After replacing the high-pressure steam preheating coil, it must be purged with steam. (Yes) 3. In a fire-tube waste heat boiler, the tube sheet on the high-temperature side is more prone to damage than that on the low-temperature side. (Yes) 4. Once a leak in the waste heat boiler is detected, the plant must be shut down for maintenance. (Incorrect) 5. In the Brown process, during normal operation, the combustion air in the first furnace is cold air. (Mistake)
Reply #52009-12-26
1. In the Brown process, the process condensate is discharged without being stripped. (Incorrect) 2. After replacing the high-pressure steam preheating coil, it must be purged with steam. (Yes) 3. In a fire-tube waste heat boiler, the tube sheet on the high-temperature side is more prone to damage than that on the low-temperature side. (Incorrect) 4. Once a leak in the waste heat boiler is detected, the plant must be shut down for maintenance. (Yes) 5. In the Brown process, during normal operation, the combustion air in the first furnace is cold air. (Mistake)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.