Thread Content
How long does it take to install a 400 cubic meter spherical tank on site? What are the procedures involved in the installation of spherical tanks? The ball skin is 30mm thick and made of Q345 material.
Storage and Transportation Engineering Technology Exchange Area » Storage and Transportation Engineering Category (Member Resource Sharing Area) » This post titled \"Summary of Inspection and Monitoring for Sphere Tank Installation\" may be useful to you. http://bbs.hcbbs.com/viewthread.php?tid=191301 It takes about 4 months to go from the on-site inspection and assembly of a 400-size spherical tank to the completion of its hydrostatic testing.
Design \ construction period for 2000-cubic-meter spherical tanks: http://bbs.hcbbs.com/viewthread.php?tid=533709. Check it out as a reference! More or less the same
The duration of construction for spherical tanks of different sizes is more or less the same; under normal circumstances, it takes about 3 months
I’ve never worked on spherical tanks before; I’m here to learn!*
It generally involves on-site assembly, on-site welding, radiographic inspection of welds, hydrostatic testing, heat treatment, airtightness testing, installation of accessories, installation of fire protection facilities, painting, and level calibration.
1. For the specific details of the construction procedures for spherical tanks, refer to the \"SHJ 512-90 Standards for Construction Techniques of Spherical Storage Tanks\"