To check the base fee for engineering design, is the amount he mentioned the total estimated cost?
Reply #22010-04-16
You’re right; generally, the direct engineering costs should be used as the base price for calculation
Reply #32010-04-17
The fee for engineering design is calculated using the following formula: 1. Engineering design fee = Base fee for engineering design × (1 ± Fluctuation range). 2. Base fee for engineering design = Basic design fee + Other design fees. 3. Basic design fee = Base fee for engineering design × Professional adjustment factor × Complexity adjustment factor × Additional adjustment factor. For more details, please refer to: **Notice by the Planning Commission and the Ministry of Construction on the Issuance of the “Regulations on Fees for Engineering Investigation and Design” (January 7, 2002; Pricing Document [2002] No. 10)**
Reply #42014-01-14
The base price for engineering design fees = (6000 – 5000) / (8000 – 5000) × (249.6 – 163.9) + 163.9 = 192.47. What does all of this represent? Please explain. Thank you
Reply #52014-01-14
There should be some data preparation ahead, right? Otherwise, it would be jarring.
Reply #62014-01-15
8000 and 5000 are two investment threshold values within the base price; 249.6 and 163.9 are the corresponding base design fees for these two levels of project cost. In other words, the base design fee for a project with a cost of 8000 is 249.6, while it is 163.9 for a project with a cost of 5000. To calculate the base design fee for a project with a cost of 6000, you use the formula provided, which is known as interpolation. You can understand this better by drawing a triangle……
Reply #72014-01-16
I see. If the investment amount is exactly 3000, then just use that number and multiply it by the coefficient, right? Also, do you have a table of engineering complexity? For our chemical industry needs, please contact fineice@163.com
Reply #82014-01-16
Yes, if the investment amount falls within a certain limit, then the corresponding base value should be multiplied by a coefficient; for details on this coefficient, refer to Document No. 【2002】10 on the Regulations for Managing Fees Related to Engineering Survey and Design, which can be found on Haichuanli
Reply #92014-01-17
Differential pricing, just like individual income tax, involves tiered charging.
Reply #102014-01-17
God’s door is broken and bidding is being prepared for repairs. Three bidders showed up. The first Indian offered 3,000; 1,000 for labor, 1,000 for materials, and he would keep 1,000 for himself ; The second German offered six thousand; two thousand for labor, two thousand for materials, and he kept two thousand for himself ; The third Chinese person offered 9,000; I’ll make a profit of 3,000. I’ll give you a 3,000 rebate, and let the Indian person handle the remaining 3,000. God was very pleased; he slapped the table and shouted, “It’s you.”

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.