What should be dealt with first in the synthesis system in case of a power outage across the entire plant?

2010-05-23View Original

Thread Content

What should be dealt with first in the synthesis system in case of a power outage across the entire plant?
Reply #22010-05-23
I don’t know what you’re synthesizing; when setting up our equipment, we first cut off the feed and then purge it with nitrogen
Reply #32010-05-23
First, close the inlet and outlet valves of the system, as well as the main valve and the quench valve leading to the synthesis tower. Then open the vent valve to relieve pressure. If the plant is shut down for an extended period, nitrogen should be used to protect the catalyst.
Reply #42010-05-23
The first thing to do is to close the ammonia synthesis valve in order to prevent accidents caused by high pressure leaking into the low pressure system

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.