How are equipment documents managed in the installation of engineering equipment? The installation unit is supposed to use the materials that come with the equipment, but often after installation they get lost or become damaged and unusable. I would appreciate some guidance from those with experience. Thanks first
The standard procedure for resolving this issue is as follows: 1. Sign a contract: 1 (O) + 6 (C). 2. In step 6(c), provide 1 copy directly with the equipment to the construction party, which will not be retrieved.
One set of blueprints can be kept, and it’s best to provide copies of the equipment documentation
I would like to share the document management regulations for the technical renovation projects of our factory’s units; I wonder if they might be of some use as a reference. Regulations on the Management of Documentation for Unit Technical Transformation Projects (I) Scope of project technical documentation: 1. Documents serving as the basis for project approval, such as project proposal applications, feasibility study reports, and project approval decisions ; Construction, quality inspection, supervision, completion acceptance, trial operation, etc ; 2 Basic inspection reports, generator rotor flaw detection reports, manufacturer (operating plant) investigation reports ; 3 Tender documents for equipment procurement, design procurement, construction procurement, and project supervision ; 4 Construction drawing design documents and materials for review and signature of drawings ; 5 Project estimate sheet, construction budget table, final project settlement statement, list of fixed assets and detailed tables ; 6 Project supervision contract, project supervision plan and implementation details ; 7 Construction organization design, pre-construction technical briefings, construction plan, construction scheme, construction technique measures ; 8 Design changes, engineering modification request forms, notification forms ; 9 Raw material inspection reports, raw material factory technical documents, product certificates of conformity ; 10 Equipment Installation Records (II) Requirements for project technical documents: 1. Project technical documents must be complete, accurate, and systematic; they should have neat diagrams, proper binding, and complete signing procedures. Descriptions should be provided for images and photos. 2 The as-built drawings shall reflect the actual conditions; it is essential that the drawings correspond to the reality. Construction records, inspection records, handover and acceptance records, as well as visas, must all be stamped with the as-built drawing seal. (1) Construct in accordance with the drawings; if there are no changes, use the original construction drawings as the as-built drawings. (2) In the event of general design changes during construction, if they can be made on the construction drawings, the construction party shall indicate on the original drawings the parts that have been modified, along with the basis and explanations for such changes; these modified drawings can then be used as the as-built drawings. (3) In the event of any major changes such as structural changes, process changes, layout changes, or project modifications that render the original construction drawings unusable, it is necessary to redraw the as-built drawings. 3 Materials such as pictures, photographs, and videos from the implementation process, as well as major events and accidents that occurred during project implementation, should be accompanied by complete written descriptions. At the same time, the archive information registration form must be filled out in detail.
There’s no need to worry; project management has specific requirements regarding the handling of documents, with dedicated roles for design management and document management. The drawings provided to the construction team are only one set. After the project is completed and accepted, the drawings (including any accompanying equipment documentation) must be stored in an archive. There won’t be just one set of documents – this is specified in the contract
This is how we usually manage it. During the unpacking, inspection, and acceptance of the equipment, the intermediate supplier, the owner, the supervision unit, and the construction unit shall organize personnel to carry out the acceptance. Generally, the random textual materials that come with the equipment are managed by a designated person assigned by the owner after unboxing. The contractor or other relevant parties may borrow or copy it if necessary. Unboxing a device is important, but the accompanying documents are often overlooked. Its importance becomes apparent in the later stages of the project and after production, when issues with the equipment are discovered. Also, records must be kept for mechanical equipment; without such information, the management of equipment records becomes nothing but a fantasy. The question raised by the original poster is very good.
Reply to 4# Zhongzhaoxing: Thank you, it’s explained in great detail
Equipment documentation is divided into manufacturing documents and installation documents. Manufacturing documents are usually shipped along with the equipment, while installation documents require signatures from the general contractor, the supervisor, and even the owner; they generally need to be synchronized with the installation progress of the equipment