I’m currently working on an ethylene oxide project, and I would like to ask if there are any particular things to keep in mind when it comes to piping

2010-06-08View Original

Thread Content

As the title suggests, thank you all for your help.
Reply #22010-06-08
EO is a flammable and explosive chemical; 100% radiographic inspection is required for the welds of EO pipelines!
Reply #32010-11-17
There is an article titled \"A Brief Discussion on the Key Points of Designing Chemical Plants Using Ethylene Oxide as a Raw Material\" for your reference; it can be found online.
Reply #42013-06-29
Install as few valves as possible on the EO pipeline to reduce leakage points. If there is an EO leak, the current leaking pipeline must be purged before the valve can be removed or installed. The installation location of the valve needs to be considered as a whole.
Reply #52013-06-29
EOEG pipes are generally made of seamless tubes. Recently, our company signed a contract with Sinopec Shanghai Petrochemical for EOEG duplex steel pipes, which are used in heat exchangers

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.