This post was last edited by Benben Xuan on 2010-6-30 at 13:33. Petroleum installation rates: I used a such rate in Shenjimiaosuan, namely 2-1-78 for manual cleaning when the volume of oil to be removed is over 50 tons; the base price is around 6 yuan. But it’s not included in the five volumes of the oil quota standards. I’m reaching out to everyone now to ask if anyone can help me find out the origin of these quota standards. Under audit, focusing on the argumentation issue. Thank you thank you thank you thank you
After asking around extensively, I have come to a conclusion, and I’d like to share it with you all now. This quota was supplemented by the Shengji Miaosuan software team based on the supplementary quotas provided by the Xuzhou Petroleum Bureau. I would like to ask everyone whether such supplementary quotas issued by local petroleum bureaus can be used as a basis for project settlement, in cases where the project is not handled by that particular petroleum bureau
First, you need to check what your contract stipulates, to see if there is any provision stating that when the specified budgeting software cannot be used to determine the corresponding line items, similar standard line items can be referred to. You are in Shandong; you use Xuzhou’s quota database, and it’s difficult to explain the situation when there isn’t a proper connection. There’s another issue: how do you ensure that your estimates and final accounts are error-free? Theoretically, this is good, but at a deeper level, it’s because your *system isn’t in place. There are ways to identify sub-items that are not included in the standard list, and everyone has their own way of understanding this. My master understood it as the writing style of each person.