Regarding the construction delay issue

2010-07-16View Original

Thread Content

Our company is building a new chemical plant, and due to rain sometimes, the construction team submits requests for delays on the grounds that work cannot proceed because of the rain. I’m not sure under what circumstances rain can justify a delay in construction – does just one day of rain count? Please share your valuable insights.
Reply #22010-07-16
Reply 1# fujq07: No, it’s something they must take into account. When working on construction projects, if you don’t even know the local climate, such as the rainy season, then how can you carry out those projects? If it’s postponed by 1 month next month, that would be fine. Back when we were working under a tight deadline, we would go out in the rain as well; if there were difficulties, we could discuss ways to solve them instead of acting as if it wasn’t our concern.
Reply #32010-07-16
Experienced contractors are able to anticipate common difficulties (such as the rainy season) and take corresponding measures and contingency plans in their construction plans to avoid the potential risks that such difficulties may pose to the project. Therefore, the request submitted on the first floor regarding the construction team’s delay due to rain cannot be approved; instead, the contractor must be instructed to carry out the work strictly in accordance with the requirements. Unless the project site is hit by once-in-a-century severe weather, then the contract’s “force majeure” clause applies.
Reply #42010-07-16
It depends on how heavy the rain is; if it causes disasters, then it can be considered
Reply #52010-07-19
Reply to 1# fujq07: I disagree with the view above. When it comes to constructing elevated pipeline systems for industrial processes, welding is of great importance. If you are working in the south, rainy weather is quite common. During the summer now, it rains every 2.3 days. Do you really think you can build a shelter on top of the utility tunnel? Besides, when strong winds blow, it’s impossible to stand steady; it would be strange if no one flew kites in such conditions. Say it again. It’s just a light drizzle, and the supervisor as well as the client’s welding inspector have ordered that work stop. Catch you once, and I’ll execute you.
Reply #62010-07-19
Hehe, this question can be answered from two perspectives: First, regarding unplanned stoppages due to rain or other factors, such issues should be settled during contract negotiation and signing, with both parties agreeing on the relevant terms. As the saying goes, \"it’s better to mention unpleasant things upfront.\" If project management is to be carried out strictly in accordance with the contract terms, detailed considerations must be made beforehand; II. Consider the urgency of the project; generally, the construction of projects requires a planned schedule. If a project is very important for your company’s operations this year – for example, if it has a direct impact on production capacity, safety, or profitability – and a one-day suspension of work would cause significant problems, then every effort should be made to avoid such suspension. As for cases where some contractors deliberately look for reasons to halt work, action should be taken against them, as the contract certainly stipulates the rights of the client. This aspect of the contract is indeed worth careful consideration. Specifically, in cases where rain occurs during work, a shutdown request should be submitted only if the rain affects the quality of construction; if construction can proceed by taking appropriate measures, such shutdown requests should be rejected.
Reply #72010-07-20
It depends on the specific circumstances. According to the contract template, if an force majeure event occurs that the contractor cannot foresee, the deadline should be extended.
Reply #82010-07-21
Reply to 3# WiseOne: It depends on how heavy the rain will be, as well as the probability of such an occurrence in history; if it’s very low, then it should be taken into consideration.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.