Regarding the startup of the pump, I’d like to ask everyone for advice

2010-07-29View Original

Thread Content

For starting the pump, there are two methods: soft start via the PLC and hard start via the control panel. Can the wiring for these two starting methods be connected in parallel at the PLC’s terminal block? I’m a beginner, haha. Also, roughly how many devices can a PLC control cabinet of size 2100x800x800 control? Is there an approximate figure? Of course, it is related to signals; some require safety barriers, while others need relays, etc. . . I’m just asking for a rough estimate here
Reply #22010-07-30
It should be configured as a tandem setup, not just a simple parallel connection. The number of I/O points in a PLC depends on the number of control points you have, as well as the size of the PLC and the number of expansion modules used
Reply #32010-07-31
Ha, thanks for your answer, hehe

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.