Adipic acid issue

2010-08-09View Original

Thread Content

Dear Haiyou friends, I would like to ask: for two sets of 75,000-ton capacity plants that start with purified benzene, proceed to cyclohexane, and ultimately produce adipic acid, including facilities for hydrogen production and nitric acid production as well, what is the approximate floor area required for these plants? How many people are needed? Thank you.
Reply #22010-08-09
Reply 1# tsxysxl: The proportion occupied by related utility systems is also quite large
Reply #32010-08-09
Reply to 2# shangdongde: I’m not sure if you have the specific data; could you please send it to me? Thank you.
Reply #42010-08-12
The factory covers an area of about 35 hectares and requires 650 employees, with the number of employees in state-owned and private enterprises varying.
Reply #52010-08-12
Your footprint is a bit large! The design institute said that 17-18 hectares of land would be sufficient, and this refers to the total area required. But what is the floor area? How many people are needed?
Reply #62013-09-27
700 mu of land, about 900 people – that’s our factory

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.