Factory acceptance criteria for reciprocating compressors

2010-10-17View Original

Thread Content

I have purchased several reciprocating compressors, which are now ready for incoming inspection. May I ask everyone, what aspects should be focused on during this inspection process? I hope everyone can offer me plenty of guidance
Reply #22010-10-17
Once the goods arrive, do not open the box yet; wait until the technical staff from the pump manufacturer arrives. Inside the box there is an inventory list, which should be taken out and checked item by item. If everything is correct, then sign it
Reply #32010-10-19
The acceptance process in a compressor factory simply involves running the machine for a few hours without load. The main aspects of this inspection include checking its operating conditions and, after it has been run, examining the wear on various components.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.