Latest Progress on Datang International’s Dulun Coal-to-Methanol Project

2010-10-19View Original

Thread Content

This post was last edited by 654262293 on 2010-10-21 at 13:10. What is the latest progress on the Datang International Dulun coal-to-methanol project? Who knows when we’ll drive? I’d really like to know!
Reply #22010-10-20
It’s running; it’s supposed to start operating this year, but it seems it can’t start – it’s already snowing over there.
Reply #32010-10-20
I heard there was an incident not long ago, with an oxygen pipeline exploding; I’m not sure if it’s true
Reply #42010-10-20
Is that factory located there? Who knows?
Reply #52010-10-21
Is the information on the 3rd floor reliable? Oxygen pipelines are indeed one of the more dangerous elements; there are numerous construction procedures involved, and strict controls are required – no carelessness is allowed at all
Reply #62010-10-21
This post was last edited by 654262293 on 2010-10-21 at 13:10. I heard that Shell’s powder gasification process is being used for gasification, but operations have not been very good; efforts are being made to improve gasification performance. Does anyone know the details?
Reply #72010-10-21
Reply to 6# 654262293: I remember meeting someone named Xiao** from Datang during a business trip outside. I asked about their production processes, and it seems they have 3 Shell furnaces with a capacity of 500,000 tons each, along with 3 conversion units installed downstream! That’s so impressive; amazing! And there are many downstream products as well
Reply #82010-10-21
I think there’s no need to avoid things when problems arise; anyway, one has to face everything. Besides, it’s impossible for a factory to have no problems at all; we’ve encountered many problems as well. As long as one approaches things with the right mindset, any problems that arise aren’t necessarily one’s own fault – it’s inevitable to make mistakes sometimes. What’s the progress now? What does it look like now? Can someone from Datang Haiyou come and talk about it?
Reply #92010-10-23
Checking…… There are quite a few issues with the Shell furnace; the Lurgi MTP will be installed later.
Reply #102010-11-27
Tulun seems to be in Inner Mongolia; it’s a shame I’ve never been there
Reply #112010-11-27
Reply to 4# zhaohaiwei: In Duolun County, Inner Mongolia! After Zhangjiakou, head further north! It’s not very far from Beijing – 7 hours by car!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.