This post was last edited by Shutong on 2011-1-4 at 12:38. The completion documents refer to the final drawing and documentation files after a device (unit) has been completed; they do not include (). A. Project completion documents B. Design completion documents C. Procurement completion documents D. Construction completion documents Notes on daily topics in the quality area: 1) Participants must be rewarded: A reward of 5–20 points is given for the topic post of each day, or more as appropriate; for correct answers to multiple-choice questions, scores are assigned based on the order of responses: 2nd floor: 10 points, 3rd floor: 9 points, 4th floor: 8 points, 5th floor: 7 points, 6th floor: 6 points, floors 7 and above: 5 points. No score is given for incorrect answers. Doubling of detailed descriptions and sources is available. No scoring will be given for replies on the second day. 2) Please hide your replies; the method for doing this is: http://bbs.hcbbs.com/thread-492556-1-1.html 3) Do not edit your replies after posting them, as replies that are edited will not be scored. 4) Due to the busy work of moderators, they can move posts down on the following day. 5) Please ask the moderators in the Quality section to post actively and provide ratings promptly, especially for topic posts that were not posted by them themselves. Moderators are reminded to mark processed posts as read to avoid redundant work. P; 。 9. Spamming posts should not be encouraged; the moderators should merely issue reminders. Points can be deducted, warnings given, and posts deleted in cases of malicious spamming. These are the key measures used in quality-focused areas to encourage the posting of legitimate content. 6) Members are welcome to propose daily topics. These topics should be rich in content and not be limited to multiple-choice questions; more discussion-based content and Q&A posts should be included to encourage participation from other users
A According to the safety engineer examination, as-built documents refer to the final drawing and documentation prepared after the design, procurement, and construction of a plant (unit) are completed. They mainly consist of three parts: design as-built documents, procurement as-built documents, and construction as-built documents. So choose A