HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

How to register pressure vessels for new installations

2011-01-11View Original

Thread Content

As the title suggests, once the new installation is in place, how should pressure vessels be registered? Which party is responsible? Thank you!
Reply #22011-01-11
Do you mean after the container is installed? In that case, it’s necessary to take the blueprints, completion documents, and other relevant materials to the Special Equipment Department of the Technical Supervision Bureau to proceed with registration; once registration is completed, a registration number will be issued to you, and then the container can be used
Reply #32013-06-16
May I ask: Is it the installation unit or the user unit that is responsible for handling the registration for newly installed equipment and pressure pipelines?
Reply #42013-06-17
The installation supervision and inspection of containers is generally the responsibility of the construction party. After the installation supervision and inspection are completed, the user unit issues the usage certificate, as this involves matters such as personnel management and training for the users.
Reply #52013-06-18
Generally, it is the construction unit that handles the registration process, but in some cases, it is the construction company that is responsible for this task, such as my current construction unit. Generally, registration requires the seal of the construction unit or its identification documents; requirements vary from region to region
Reply #62013-06-18
Registration is handled by the entity that uses the equipment (the owner of the equipment). The documents required include: the technical documentation provided with the pressure vessel at the time of manufacture (quality certificate, inspection report issued by the local authority responsible for inspecting special equipment, strength calculation documents, etc.), the installation notification, and the report confirming that the installation was carried out in compliance with regulations.
Reply #72014-05-14
The owner goes to register, and the user unit goes to register. The required materials are far more than what was mentioned above; there are also many things such as personnel qualifications and management systems. Emergency plan. . . Wait. What was said upstairs are the main materials. The quality supervision bureau takes one set of documents, and it also demands many other documents that one might not expect, such as construction permits and the like; they find ways to make companies prepare more documents. . . It demonstrates **effective supervision, truly serving businesses!** !
Reply #82014-05-20
The last edit to this post was made by haidisixhq on 2014-5-20 at 10:50. The entity that will use the equipment should go to the local technical supervision bureau to complete the necessary procedures. After receipt, the entity in question must provide quality certification documents related to the equipment, as well as inspection certificates, issued by the manufacturer; a representative from the technical supervision bureau will then visit the site

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.