I would like to ask: For a newly established enterprise or a project involving expansion and technological upgrading, when is the most appropriate time to formulate an emergency rescue plan for accidents?
It must be completed before the official start of trial production, and necessary drills also need to be carried out prior to commencement
Reply to 2# HappyJoker: What’s the basis for this?
Reply to 3# mzdbhmzdbh regarding the requirements of Article 24 of Order No. 8 issued by the State Administration of Work Safety. Order No. 17 of the State Administration of Work Safety is the specific management regulation.
Do you need to submit your pilot production plan to the administrative approval center? This is when the emergency rescue plan comes into play. The plan also needs to be submitted. . .
Reply to 3# mzdbhmzdbh: When conducting the completion acceptance of a construction project, both the contingency plans and drills are part of the acceptance criteria
Once you find the relevant specifications, it will be easy to compile
Reply to 4# siena2008: Thank you all; I’ve read it.
Reply to 4# siena2008: Can the on-site handling plan in the test drive plan be used as an emergency rescue plan?
Reply 9# mzdbhmzdbh is not the same thing. There are standards and guidelines for formulating emergency rescue plans. In some provinces and municipalities, evaluations are required, and the results must be reported to relevant authorities for record-keeping.
Reply to 10# siena2008: So, do you think what needs to be prepared by the unit before testing is an emergency rescue plan or an on-site response plan?