The relationship among feasibility study, environmental impact assessment, and safety assessment

2011-01-27View Original

Thread Content

Before the construction of a chemical plant begins, feasibility studies, environmental impact assessments, and safety assessments are essential steps. So what is the relationship between these three elements? Is there a distinction between them in terms of importance? Which department is responsible for approving these three?
Reply #22011-01-27
The feasibility study must come first; it is a prerequisite for carrying out all procedures. There is no distinction between environmental impact assessment and safety assessment – either one can be conducted first – but the content of both assessments is based on the feasibility study report. It is best to have a company with Class A qualifications prepare the feasibility study report for chemical projects. For feasibility studies of state-owned enterprises, approval is sought from the Development and Reform Commission; safety assessments are approved by the Safety Supervision Bureau, while environmental impact assessments are handled by the Environmental Protection Bureau. Of course, it is the Environmental Protection Bureau that has the authority to conduct such assessments, and depending on the investment amount, a different environmental protection agency will be responsible for handling it.
Reply #32011-01-27
You mention the need to distinguish between primary and secondary aspects, but if a feasibility study isn’t necessary, then there’s no need to conduct the environmental impact assessments and safety evaluations either. Therefore, when establishing a company or enterprise, the feasibility study report must be approved by the local **authorities; only with policy support can a company (enterprise) be set up. Environmental and safety assessments are supplementary, but both are essential.
Reply #42011-01-28
I’m not familiar with safety assessment. Based on my understanding, here’s how feasibility studies and environmental impact assessments work: When a company wants to launch a project, it first needs to find a qualified design firm or consulting company (it’s best to choose one that has good relationships with agencies responsible for environmental or safety assessments; this can be learned during negotiations regarding the cost of the feasibility study, or by consulting companies in the same industry). These firms are then asked to prepare a preliminary feasibility study based on factors such as investment costs, location, wind direction, groundwater conditions, and environmental emission requirements. After that, experts are brought in to evaluate whether there are any significant issues with the plan; the extent of this evaluation depends on the scale of the project – for larger projects, it’s better to involve industry planning agencies or specialized organizations to carry out this assessment. It’s also advisable to seek feedback from experts within the environmental or safety assessment systems (at the ** provincial or national level, depending on where the project is located). Once everything is approved, the contents of the feasibility study along with related documents are compiled into an environmental impact assessment report, which is then submitted to the relevant environmental authorities for review. There may be slight differences depending on the industry. For example, the Environmental Assessment Center of the Ministry of Environment,
Reply #52011-01-28
Agree with what was said above. For unapproved projects, private enterprises generally do not conduct feasibility studies; if one is to be carried out, it is done by the company itself or through the preparation of a project plan. If the board of directors requires it, a design firm or consulting agency will be engaged to carry out the study. As long as the project’s feasibility study is approved, or the Development and Reform Commission issues a registration certificate, it means that the site selection for the project has been finalized and the environmental impact assessment has been completed; only after that should consideration be given to conducting a safety assessment.
Reply #62011-01-29
The situation regarding state-owned enterprises is basically clear now; a feasibility study can be conducted next. The feasibility study should be prepared in such a way that it will definitely be approved, and if there are issues, they can be addressed through revisions. Units qualified to conduct feasibility studies are familiar with the standards for environmental impact assessments and safety evaluations, so the feasibility studies they prepare will surely be approved. Feasibility study is the most important! Environmental and safety assessments involve using data to apply formulas; there’s not much technical complexity involved. It’s just their chapters that work.
Reply #72011-01-29
Different regions have their own environmental quality standards and pollutant emission standards; generally speaking, environmental impact assessments should still be carried out by local environmental assessment agencies.
Reply #82011-01-29
Do not underestimate environmental impact assessments; in my experience, if the work of environmental assessment experts is not done properly, it becomes much more difficult to get a project approved, especially for those projects that involve issues that can be either minor or significant. As a supplementary note, after the feasibility study is approved, it is generally necessary to prepare another dozen or so documents, such as the baseline emission figures for the location where the testing will take place (background monitoring). These documents then become part of the environmental impact assessment materials, which are reviewed one by one; ultimately, the feasibility study itself is approved after all these reviews are completed. All materials must pass.
Reply #92011-02-11
Of course, the environmental protection agency that conducts the assessment has the authority to do so; different investment amounts require consultation with different environmental protection departments. The second floor provided quite detailed explanations, but I don’t quite agree with that statement; the choice of the entity responsible for environmental impact assessment is not determined by the amount of investment, but rather by the severity of the environmental impact. In recent years, the importance of environmental impact assessments has grown significantly. Many projects have passed their feasibility studies, but were rejected due to failing environmental impact assessments.
Reply #102011-02-12
Feasibility study is of primary importance, but the content and materials involved are not as complex as those in environmental impact assessments and safety assessments. In terms of significance, safety assessments are actually more important than environmental impact assessments. New projects must go through a feasibility study report, a preliminary safety assessment report, and so on; subsequently, there is also a requirement for an acceptance report regarding safety facilities. The process is quite complex and cumbersome. The environmental impact assessment report is mainly intended to obtain approval from the environmental protection agency, while the subsequent acceptance procedures are relatively simpler.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.