How long does it take for a chemical plant to go from foundation laying to operation?

2011-04-25View Original

Thread Content

This post was last edited by mqxchzhi on 2011-4-25 at 10:48. The main processes in a chemical plant (for coal-to-natural gas production) include coal preparation, gasification, shift cooling, purification via low-temperature methanol washing, SNG synthesis, and TEG drying. There are also auxiliary facilities such as thermal power units, air separation plants, electrical systems, water treatment units, instrumentation systems, and a central laboratory. The entire process involves everything from foundation laying and civil construction to equipment installation and piping work, followed by purging and commissioning. I would like to ask those with experience – the veterans in this field – how long the fastest possible time frame for this entire process is
Reply #22011-04-28
First, it is necessary to determine whether the project you mentioned has been approved Secondly are the environmental impact assessment reports for land, water and electricity, roads, and water resources. . . . They all fall under the preliminary procedures. Once these conditions are met, it depends on your scale, the timing of equipment ordering, the construction plan, and the commissioning process. . . .
Reply #32011-04-28
Reply to 2# 77544877: It has been approved by the National Development and Reform Commission, and the civil engineering work has already begun; the equipment is arriving one after another. . .
Reply #42011-05-06
If the time required for the **approval process is excluded, it generally takes three years (in the north) or two years (in the south). It is also affected by the efficiency of corporate operations; generally, private enterprises are much faster than state-owned enterprises.
Reply #52011-05-06
State-owned enterprises usually take three years, which is considered fairly quick; the key factor is the equipment drawings. Private enterprises generally take one to two years

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.