Long-life equipment for power distribution in petrochemical enterprises

2011-04-28View Original

Thread Content

Among the power distribution equipment used in petrochemical enterprises, do 35kV/6kV power distribution transformers count as long-cycle equipment, and what is their typical ordering cycle? Additionally, what is the lead time for ordering a 15,000 kW steam turbine generator?
Reply #22011-04-28
It is a long-cycle device. The ordering cycle needs to be consulted with the equipment manufacturer.
Reply #32011-04-28
When placing an order, you can ask the manufacturer; about half a year, I guess.
Reply #42011-04-28
Transformers are generally available for delivery within 2-3 months

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.