What issues should be considered when installing a heat exchanger?

2011-06-07View Original

Thread Content

What issues should be considered when installing a heat exchanger?
Reply #22011-06-07
First is the acceptance of the foundation and heat exchanger, including its appearance, as well as checking whether the spacing of the embedded foot bolts is within the allowable error range relative to the distance between the bolt holes in the equipment base. It is necessary to check whether the mass of the monolithic concrete foundation is satisfactory, whether the reserved height falls within the allowable error range, whether the exposed height of the anchor bolts is sufficient, and what distance should be left for the locking nuts, as some heat exchanger supports have shims and slides underneath them. Check that the specifications of the shims are complete and that the number of layers does not exceed the limit. It is also necessary to determine the sliding end and the fixed end, as well as to adjust and level the heat exchanger; this can be done using U-tubes or a level. Finally, organize the materials.
Reply #32011-06-07
Have there been any standards established for learning*?
Reply #42011-06-08
It is necessary to consider whether there is a core extraction location and whether space has been reserved for piping
Reply #52011-06-08
SHT 3542-2007 Technical Specifications for the Construction of Installation Projects for Petrochemical Static Equipment – it can be used as a reference
Reply #62011-06-09
Check whether the owner requires on-site pressure testing; it’s quite troublesome
Reply #72011-06-09
Check whether the owner requires on-site pressure testing; it’s quite troublesome
Reply #82011-06-10
Levelness, as well as the slippage of the sliding plate and bolts at the sliding end – 2-3 turns of looseness after fixation
Reply #92011-06-13
The position must be horizontal; if it cannot be made horizontal, then at least when the device is not in use, there should be no liquid accumulation inside the U-tube. Confirm the locations of the pipes for the cooling medium and the substance being cooled.
Reply #102011-06-15
What was mentioned on the 4th floor is correct; if core extraction is possible, the location for core extraction needs to be considered.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.