For lifting equipment weighing over 300 tons, the wire rope to be used is

2011-06-22View Original

Thread Content

I’m seeking help from colleagues who have experience in lifting equipment weighing over 300 tons – I need the steps for selecting steel cables as well as the calculation formulas used. Please upload it. Thank you
Reply #22011-06-22
The load on the steel wire rope should be calculated based on the lifting procedure, with a safety factor of 5 to 5.5 times.
Reply #32011-06-23
How many lifting points does your equipment have, and it also depends on what the lifting plan is!
Reply #42011-06-23
For equipment this heavy, it is necessary to contact a professional lifting company to develop a specialized lifting plan
Reply #52011-06-27
A specialized lifting plan needs to be developed for the several lifting locations.
Reply #62011-06-27
300 tons requires hiring professionals to do this job!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.