Installation issues with the DCS console

2011-06-25View Original

Thread Content

The bottom of the DCS console should be installed on the structural embedment foundation, but the control room requires an anti-static floor with a thickness of around 250 mm. If the console is not installed in this way, it will sink more than 200 mm below the surface. How should the console be installed in such a situation? Please help
Reply #22011-06-29
Please hire professional construction teams to do it; this is something they should take into consideration!
Reply #32012-11-13
Under the DCS installation platform, construct a steel frame that is 250 mm high; the length and width of this frame should be the same as those of the DCS installation platform. Then, fix the DCS installation platform to this steel frame. The shelf is fixed to the embedded parts.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.