What specific tasks are usually carried out on power plant boilers from after the hydrostatic test to before the 168-hour test?

2011-06-26View Original

Thread Content

This post was last edited by zgj2405 on 2011-6-28 21:10. What specific tasks are usually carried out on power plant boilers from after the hydrostatic test until before the 168-hour test? I saw this question elsewhere, and I’d like to ask again: what does “168” refer to in the context of boilers?
Reply #22011-06-27
This post was last edited by dongjiang1001 on 2011-6-27 at 10:42. 168 refers to 168 hours of full-load testing; once this is successful, the process can proceed to the trial production phase. The main tasks from the hydrostatic test to the 168-hour trial operation period include: insulation work on the boiler body, flue and air ducts, as well as steam and water pipelines; acid cleaning of the boiler; individual unit and subsystem trials of the equipment in the boiler area; ignition and pipe flushing; no-load testing alongside the start-up of the entire power plant; load-testing; and load-shedding tests along with the turbine, along with full-load operation trials.
Reply #32011-06-28
This post was last edited by dongjiang1001 on 2011-6-28 at 20:01. It includes secondary sealing, improvement of the final pipeline section, insulation work, masonry, furnace drying, pickling, pipe cleaning, restoration and defect correction of the pipelines. It also involves individual unit tests, partial system tests, subsystem tests, and finally a 168-hour comprehensive trial operation. The “168” for a boiler refers to its 168-hour trial operation.
Reply #42011-07-01
The hydrostatic test merely marks the completion of a phase-specific task related to the boiler itself; in terms of the entire boiler system, only half of the work has been completed. Tasks such as the improvement of platform escalators, pouring, installation of blowers and exhaust fans, fabrication and installation of smoke and air ducts along with sealing tests, defect correction, use of baking ovens, purging of main steam pipes, and restoration of pipes.
Reply #52011-07-04
It can now also run at full capacity for 92 hours. After the hydrostatic test, insulation work is carried out on the furnace body, flue and air ducts, as well as steam and water pipelines; followed by single-unit testing, as well as operations such as baking the furnace and pipe flushing

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.