The last edit to this post was made by lijianhuai on 2011-7-6 at 10:29. I would like to ask the experienced colleagues: what size of projects in the field of oil refining and vacuum distillation are not allowed to be carried out these days?;
As long as there is a connection, one can join; there should be people in this field on the chemical engineering forum: http://bbs.hg707.com
It’s stipulated that those below 5 million tons aren’t allowed to proceed, right?
Reply to 3# Trace elements: It seems to be around 800 watts per ton, I think so.
Our affiliated company plans to dismantle the small unit and build a 3 million-ton atmospheric and vacuum distillation unit; it’s likely what the colleague upstairs mentioned – approvals can be granted if there is a connection
The 800W ton project in the catalog will not be approved. Currently, local refineries are applying for approvals to produce over 1.5 million tons in the form of heavy traffic asphalt and raw material pretreatment. But the situation is not easy to handle now either; the National Development and Reform Commission is also aware of these tricks. It’s related; upstream and downstream devices are also necessary.
It’s very difficult to get approval for new projects. Currently, many local refineries are being built to process fuel oil.
**It is required that no approvals be given for projects of 8 million tons or less; however, it is possible to replace a smaller facility with a larger one by demolishing the smaller one and constructing a larger one in its place. It is also possible if upstream and downstream equipment need to be matched. It’s mainly a matter of wordplay; (for example: projects involving the production of olefins from heavy oil, or aromatic compounds) as long as there is a connection
Please take a look at this post: Theoretically, 80% of domestic atmospheric and vacuum distillation units are facing elimination http://bbs.hcbbs.com/viewthread.php?tid=854355&rpid=5936203&ordertype=0&page=1#pid5936203pid5936203
Why not check the restrictions on refining projects in the 12-5 plan? I posted this thread; the original poster should check it themselves.